Posted by: Stan Russell | May 15, 2013

UPDATE #31 HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT

CALTRANS NEWS RELEASE
Today’s Date:
Wednesday, May 15, 2013 at 9:15 am
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189

SPANISH TRANSLATION ATTACHED

FOR IMMEDIATE RELEASE

** UPDATE #31 **
HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, May 20 through Friday, May 24 with 10-minute delays as needed.

NOTE: There will be NO OVERNIGHT FULL closures next week, but there WILL be NIGHT ROADWORK and traffic may be held for up to 10-minutes as needed from 9 pm to 7 am, starting Monday, May 20 through Thursday, May 23 (Friday 7am). No overnight closures on Sunday, May 19.

The closures/delays are needed to move equipment and materials to construct a soldier pile wall.

Highway 1 at Rocky Creek has one-way signalized traffic control 24/7. Traffic will be stopped for 10 minutes at a time during daytime roadwork. Full overnight closures will be scheduled five nights a week Sundays through Thursdays, unless otherwise indicated. No overnight closures will occur on Friday/Saturday nights.

The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4. Completion is scheduled for the end of October, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates.

The contractor for this $11 million viaduct project is Golden State Bridge of Martinez, CA.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information, please visit: http://www.dot.ca.gov/dist05/paffairs/ orcontact the Hwy. 1 Cambria to Carmel Toll-Free Hotline at 888-836-0866.

Falsework Removal-5.14.13

Completed Viaduct Railing-5.14.13

sp_rockycreek_update31_5_15_13.doc

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: