UPDATE #59 ** HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT IS COMPLETED

Today’s Date: Friday, November 22 at 9:15 am
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties
Contact: Susana Z Cruz (bilingual) or Jim Shivers
Phone: (805) 549-3138 or 549-3189

FOR IMMEDIATE RELEASE

* UPDATE #59 **

HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT IS COMPLETED

NOTE: All work requiring lane closures has been completed. Very little work is left on the hillside clearing debris.

The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4, 2012. Completion was scheduled to occur at the end of October. The project is 100% complete. The temporary signal has been removed.

The contractor for this $11 million viaduct project is Golden State Bridge of Martinez, CA.

CALTRANS WISHES TO THANK THE BIG SUR COMMUNITY FOR THEIR PATIENCE DURING THIS PROJECT.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information, please visit: http://www.dot.ca.gov/dist05/paffairs/ orcontact the Hwy. 1 Cambria to Carmel Toll-Free Hotline at 888-836-0866.

BEFORE: March 2011–damaged roadway
Picture courtesy Of Stan Russell

AFTER: Nov. 2013–Looking northbound and southbound with viaduct completely open

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: