Today’s Date: Friday, December 19, 2014
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE
SLIDE REMOVAL AND DRAINAGE WORK ON HIGHWAY 1 BETWEEN MONTEREY/SAN LUIS OBISPO COUNTY LINE AND GORDA THIS WEEKEND
MONTEREY COUNTY– A maintenance project to remove slide material and perform drainage work will take place on a 10-mile section of Highway 1 between the Monterey/San Luis Obispo County line and Gorda tomorrow, Saturday, Dec. 20 and Sunday, Dec. 21, Caltrans officials have announced.
Work hours are from 7 am to 3 pm both days under one-way traffic control with flaggers. Motorists can expect a delay not to exceed 15 minutes. Electronic Message Boards will be activated to alert motorists.
The purpose of this two-day emergency project is to clean up after the recent batch of storms and will be performed by the Willow Springs and Templeton North maintenance crews. This emergency roadwork is necessary to ensure all of the maintenance needs of the coast highway area are met. Work will be completed on Sunday afternoon, Dec. 21, weather permitting.
NOTE: Access to businesses will remain open via Hwy. 1 between Ragged Point and Big Sur
Caltrans reminds motorists to move over and slow down when driving through highway construction zones.
For more information on this project and for traffic updates on other Caltrans projects in Monterey County, residents can call the District 5 toll freenumber at 1-831-372-0862 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon
# # #