Posted by: Stan Russell | March 12, 2017

Daily Trail Progress Update

March 12, 2017

Daily trail progress update.

More progress was made again today on the access trial work. Work was started on two to three more series of steps in addition to more work on the actual trail. There were 9 volunteers today led by Fire Brigade Lieutenant Marcus Foster.

Approximately 1/2 of the trial has been put in already. Marcus reported the top part of the trail was looking very good.

The work and progress on the trail will be reevaluated daily.

Trail crew lead recommends a hard closure of the trail on Monday March 13th during bridge demolition.

In addition:

The below statistics on the update for the Pfeiffer Canyon Trail as of 12:00 pm today, March 12thprovided by State Parks.

  • Total Trail tread completed: 739 linear feet
  • Total Trail tread completed today: 167 linear feet
  • Total heavy brushing completed: 1539 linear feet
  • Total light brushing completed: 778 linear feet
  • Total number of workers on trail: 13 CCC, 9 volunteers, 4 DPR
  • 11 Wood crib steps have been completed

Brent Marshall; State Parks; Martha Karstens, Big Sur Fire Brigade; Gerry Malais, Monterey County Office of Emergency Services – Unified Command

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: