HIGHWAY 1 UPDATE – MONDAY, MAY 22 AT NOONTIME– PAUL’S SLIDE FUTURE ACCESS DEPENDEN T ON SAFETY

*A news release is attached (and shown at bottom of email) on the third and fourth convoys—scheduled for Tuesday and Thursday of this week.*

HIGHWAY 1 UPDATE – MONDAY, MAY 22 AT NOONTIME– PAUL’S SLIDE FUTURE ACCESS DEPENDENT ON SAFETY.

PAUL’S SLIDE ROADWORK HAS CEASED DUE TO SLIDE ACTIVITY WHICH HAS INCREASED. THE ROADWAY WILL BE ASSESSED AT EACH SCHEDULED ACCESS TIME (SHOWN BELOW), BUT IF ROADWAY IS DEEMED UNSAFE, SUCH AS MATERIAL COMING DOWN, LOW VISIBILITY DUE TO EXCESSIVE FOG OR SLIDE IS BEING ACTIVE, LOCALS/DELIVERIES WILL NOT BE ALLOWED THROUGH. FOR EXAMPLE, FOR TODAY’S EVENING ACCESS, LOCAL RESIDENTS CAN LINE UP, BUT IF MATERIAL IS COMING ONTO THE ROADWAY OR PAUL’S SLIDE IS ACTIVE, LOCALS WILL NOT BE GRANTED ACCESS.

STATE ROUTE 1 REMAINS FULLY CLOSED IN BOTH DIRECTIONS AT MUD CREEK DUE TO CONTINUED SLIDE ACTIVITY. DELIVERY VEHICLES AND LOCAL RESIDENTS WILL NEED TO USE NACIMIENTO-FERGUSSON TO EXIT SOUTH OR TO CLEAR THE ACCESS TIMES AT PAUL’S SLIDE.

THE INFORMATION BELOW IS FOR LOCAL RESIDENTS AND DELIVERY VEHICLES ONLY;THE ONLY ACCESS TO THE PUBLIC REMAINS THE SAME AND IS SHOWN IN BRACKETS BELOW.

· [Public access on Highway 1, using Nacimiento-Fergusson, will be to Gorda (PM 10) to the south, and to Limekiln State Park (PM 20) to the north.]

************************************************************************************************

· Mud Creek (PM 8.9) – MUD CREEK HAD A MAJOR SLIDE/SLIP OUT AT 9:30 PM, SATURDAY, MAY 20—IT LOST MILLIONS OF CUBIC YARDS OF MATERIAL AND REMAINS IMPASSABLE UNTIL FURTHER NOTICE.

·

Paul’s Slide (PM 21.6)—ACCESS FOR LOCAL RESIDENTS AND DELIVERY VEHICLES

ONLY.

PAUL’S SLIDE HAS ALSO HAD SLIDE ACTIVITY OVER THE LAST WEEK AND HAS CEASED WORK FOR THE TIME BEING. HOWEVER, IT WILL ALLOW LOCAL RESIDENTS AND DELIVERY VEHICLES ACCESS WHENEVER IT IS DETERMINED TO SAFELY DO SO BUT CAN CLOSE DOWN AT ANY TIME WITHOUT PRIOR NOTICE (SEE UPDATE ABOVE). CALTRANS NEEDS TO RE-ASSESS THE SITUATION AT BOTH LOCATIONS AND DETERMINE WHETHER LOCAL ACCESS CAN REMAIN THROUGH PAUL’S SLIDE. NEXT UPDATE WILL BE BY MID-DAY ON TUESDAY, MAY 23.

Work on the slope continues. The targeted “public access” date of mid-to-late-June needs to be re-assessed with recent activity, public opening date could be pushed further out.

· 12:00PM Monday / Wednesday / Friday– A single caravan south and a single caravan north, you must be in line by noon! There may be up to 45 minute delay to clear the road before the opening.

· Delivery vehicles (Restriction is 30 feet maximum length and 50,000 lbs. maximum weight) can now use all access windows 7 days a week.

· Access times for the morning and evening are still the same except for Friday:

5:30AM to 6:00AM and 7:00PM to 7:30PM – Sat.-Thurs.

· Friday’s hours will be shortened to:

5:30AM – 8:00AM and 6:00PM to 7:30PM

· The noon opening will be for PAUL’S SLIDE ONLY, (NOT MUD CREEK); you will need to use Nacimiento-Fergusson Road to exit the coast.

Today’s Date: Monday, May 22, 2017

District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa

Cruz Counties

Contact: Susana Z Cruz (bilingual) or Colin Jones

Phone: (805) 549-3138 or 549-3189

FOR IMMEDIATE RELEASE

*Update #3*

CALTRANS ANNOUNCES NEXT CONVOY TO PFEIFFER CANYON BRIDGE

MONTEREY COUNTY – Caltrans will continue the process of delivering construction equipment and materials to the site of the demolished Pfeiffer Canyon Bridge on State Route 1 via Nacimiento-Fergusson Road from US Highway 101 on Tuesday, May 23 and Thursday, May 25.

These convoys will be escorted by the California Highway Patrol (CHP) and will include intermittent closures of Nacimiento-Fergusson Road on Tuesday, May 23 from 7:30 am to 3 pm and on Thursday, May 25 from 8 am until 7 pm. Motorists wishing to travel east/west in the morning must do so before the first convoy begins. On Thursday, motorists will encounter delays during the movement of these four convoys westbound from 8 am to 10 am and 2 pm to 4 pm and eastbound from 11 am to 1 pm andfrom5 pm to 7 pm. All vehicles must not exceed 30 feet in length and a weight of 15 tons.

The Tuesday convoys will include asphalt and other materials in 10 trucks while the Thursday convoys will include the remaining 50% of the rock and sand necessary to create concrete abutments for the new bridge. Future convoys will transport two mobile batch plants, two concrete boom pump trucks, vacuum trucks and rebar cages. This equipment will be used to construct concrete abutments and overall construction of the new Pfeiffer Canyon Bridge (PM 45.52).

The steel girders for the new bridge are currently being fabricated at a plant in Vallejo, CA. They will then be moved to a plant near Stockton for painting before they are shipped to Pfeiffer Canyon. This $24 million project is expected to be open to the public in mid to late September.

Caltrans reminds motorists to move over and slow down when driving through highway

work zones.

For more information on this project and for traffic updates on other Caltrans projects in Monterey County,

residents can call the District 5 toll freenumber at 1-831-423-0396 or can visit our website at:

http://www.dot.ca.gov/dist05/paffairs/release.htm#mon

Photo of second convoy

Susana Z. Cruz

Caltrans District 5

Public Information Officer

Portavoz de Relaciones Públicas

para Caltrans en el Distrito 5

805.549.3138

805.549.3326–fax

Follow us on Facebook

We welcome your feedback: https://www.surveymonkey.com/r/RNBZG55

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: