HIGHWAY 1 UPDATE – Monday, August 7

HIGHWAY 1 UPDATE – Monday, August 7:

Highway 1 in Monterey County continues to provide 35 total miles of Hwy. 1 to the public from south of Gorda (PM 10) to just south of Pfeiffer Canyon (PM 45.5), accessible only via Nacimiento-Fergusson Road. State Route 1 remains closed from north of Salmon (just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek event. State Route 1 south of Salmon Creek is accessible via State Route 1 in San Luis Obispo County, past Ragged Point to Salmon Creek.

REMINDER: travelers CANNOT go all the way on Hwy 1 but local businesses are open on both sides of the closure points at Pfeiffer Canyon and Salmon Creek.

Mud Creek (PM 8.9)

Mud Creek had a major slide on Saturday, May 20, 2017, losing 5 million cubic yards of material. Geotechnical and radar assessments continue at the site, with a Caltrans plan to realign the existing terrain announced last week. A tentative cost and timeline is targeted to be announced at the end of August. Roadway remains impassable.

Paul’s Slide (PM 21.6)

Paul’s Slide continues to provide access to the public 24/7, with one-way reversing traffic control with flaggers.

Pfeiffer Canyon Bridge [PCB] (PM 45.52)

· Last girders continue to be trucked to the Pfeiffer Canyon Bridge construction site from near Stockton this week with girder assembly taking place in preparation for the bridge launching over the canyon.

· Public access is still on schedule for mid-to-late September.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information on this project and for traffic updates on other Caltrans projects in Monterey County, residents can call the District 5 toll freenumber at 1-831-423-0396 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#mon

Susana Z. Cruz

Caltrans District 5

Public Information Officer

Portavoz de Relaciones Públicas

para Caltrans en el Distrito 5

805.549.3138

805.549.3326–fax

Follow us on Facebook

We welcome your feedback: https://www.surveymonkey.com/r/RNBZG55

Mud Creek (PM 8.9) Construction of the seatrain rock fall barrier is complete; construction of the rock revetment continues at the north beach, which will protect the fill below the new highway alignment. Work on the northern cut above the north beach is halted until the rock revetment work is completed

Mud Creek (PM 8.9) Construction of the seatrain rock fall barrier is complete; construction of the rock revetment continues at the north beach, which will protect the fill below the new highway alignment. Work on the northern cut above the north beach is halted until the rock revetment work is completed

Pfeiffer Canyon Bridge (PM 45.52) Girder delivery and assembly in preparation for the launching

Advertisements

Responses

  1. Hi, this looks like a typo error.

    ” State Route 1 remains closed from north of Salmon (just south of the Ranger Station (PM 3) to just south of Gorda (PM 10) due to the Mud Creek event.”

    Shouldn’t it read “State Route 1 remains closed from north of Salmon (just south of the Ranger Station (PM 13) to just south of Gorda (PM 10) due to the Mud Creek event.”

    as the PM is increasing as you travel north. Plaskett Creek Campground is PM 13.7. Google maps shows the closure just south of there.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: